Hi I ask a question about that before but no one answered. In Sapapo/cdps0 does not consider the material available time for purchasing order.Normally purchasing order time is 10 august but pp/ds makes planning for 3 of august.how can I fix that problem?

Andreas_Krause
Advisor
Advisor
0 Kudos

Hi Gülnihal,

I am not sure how this relates to SAP S/4HANA for advanced ATP. Perhaps a complete example would help to understand the case in more detail.

Regards,

Andreas

Accepted Solutions (1)

Accepted Solutions (1)

former_member184670
Active Participant
0 Kudos

Hi,

Would you please check the planned delivery time in purchasing info record or scheduling agreement?

In addition, please check the MRP2 views - Planned Delv.Time date entered days.

Thanks,

Sundhu