S4 PPDS change source of supply PDS

carlos_perez8
Participant
0 Kudos

Hi all

PDS validities are changed after planned orders are fixed in planning board. This is creating inconsistencies when changing dates or converting into production orders because production version inS4 hana is not valid for this date.

Is there any way to modify in mass fixed planned orders to select the valid PDS?

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

A new explosion is always necessary when the existing orders need to be adjusted to reflect changes in the master data like PDS as you have.

In that case please use standard heuristic SAP_PP_021 New explosion which will reread PDS in planned order.

Best Regards,

R.Brahmankar

Answers (0)