on 07-22-2021 6:26 AM
Dear experts,
I have a scenario where we have just on plant with a calendar with 5 workdays per week (and some public holidays).
This is OK so far for logistics and customer service.
Problem is that production (process orders) is working 7 days a week as it is too expensive to hut down production machines over the weekend.
We are not using capacities at all!
How can I set up my one plant or the process for production in that way that I can plan the production 365 days a year but do not change the plant setting with the calendar having a 5 workdays week?
Many thanks in advance.
Best regards
Patrick
Hello patrick.g,
Create a separate factory calender and assign the same in Work Center try it.
I hope it will work for your scenario.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.