cancel
Showing results for 
Search instead for 
Did you mean: 

Production planning with 7 worlkdays but 5 workdays for plant

patrick_g1
Active Participant
0 Kudos

Dear experts,

I have a scenario where we have just on plant with a calendar with 5 workdays per week (and some public holidays).

This is OK so far for logistics and customer service.

Problem is that production (process orders) is working 7 days a week as it is too expensive to hut down production machines over the weekend.

We are not using capacities at all!

How can I set up my one plant or the process for production in that way that I can plan the production 365 days a year but do not change the plant setting with the calendar having a 5 workdays week?

Many thanks in advance.

Best regards

Patrick

Accepted Solutions (0)

Answers (1)

Answers (1)

Arun_selvaraj
Active Participant

Hello patrick.g,

Create a separate factory calender and assign the same in Work Center try it.

I hope it will work for your scenario.

Thanks