By product GR and component GI at the time of phase confirmation

269 Views

Hello,

My client want to use back-flush functionality for GR of by product (531)and GI (261) of same component in the same phase.

Issue case :- He assigned same component two times to same the phase, one with positive and one with negative figures and he want to produce component as by-product (531) and then consume the same again by GI(261). But this is causing issue while GI because system is first positing goods issue and then GR of by product because of that GR gets posted successfully but GI didn’t work as there is no stock available.
what do you suggest to do in this case ..