on 06-28-2021 4:24 PM
special-procurement-40-config.png
md04-of-planning-plant-dp41.png
md04-of-planning-plant-un02.png
Dear Expert,
We have two plant DP41 and UN02.
1.DP41 is the planning plant and UN02 is the production plant.
2.In SPRO, special procurement – 40, key parameter setting for plant DP41, mention plant UN02 as the alternative plant (production plant)
3.Special procurement 40 is maintained in MRP 2 of material master of Plant DP41.
4. In MRP 2 maintains proc type = E in UN02 plant.
5.BOM & Recipe master is maintained in plant UN02.
6.Configuration of special procurement – 40 has been done as given below;
Plant: DP41 [ Planning Plant]
Sp.Pr.Type 40 - Stock transfer (proc.from alter.plant)
Procurement type F External procurement
Special procurement – U (Stock Transfer)
Plant – UN02 [ Production Plant]
7.Rolling Plan (PIR) is captured in Plant DP41 (Planning Plant)
8.Carry out MRP RUN in Plant DP41
Requirement:
9.After MRP RUN in Plant DP41, a STPR will be created in Plant DP41.
10.Planned order will show in Plant UN02 as the same is production plant.
11.Production & Procurement will be carried out in Plant UN02 on the basis of planned order.
12.Since special procurement 40 is being used, stock quantity which will be produced in Plant UN02, want to transfer from Plant UN02 to DP41 through same STPR through STO.
As per present configuration which is mentioned in point no 6.
13.PurRqs is generated in planning plant – DP41
14.PRqRel is generated in production plant – UN02, but no planned order is being generated. Since there is no planned order in plant UN02, Production is not being carried out.
I have attached herewith screen shot of Configuration and MD04 list of DP41 & UN02 for your reference.
Please help how to make step by step configuration and can resolve the issue.
Regards,
Amit Biswas
Dear Expert,
Please response .
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sundhu,
In MD02 , selected option 3 and executed MRP in Planning plant and planned order is generated. The corresponding PloRel created in production plant , MRP carried out in production plant but MRP not planned for BOM component material and giving end result " Materials with Termination MRP List " .
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Amit,
Thank you for reverting back!!
Would you please check your MRP execution in MD02, In 'Create Purchase Req.' check you selected option 3 as Planned Orders. During MRP run this triggers the Planned order instead of Purchase Req.
Thanks,
Sundhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sundhu,
I have not maintained Mixed MRP indicator in MRP3 in production plant. Only maintained Strategy Group as 11 or 10 , but this is not served the purpose.
Regards.
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Amit,
Please check the Mixed MRP indicator in MRP 3 view, this should not contain any values.
Thanks,
Sundhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Caetano,
Our main concern at point - 14.
(Point -14.PRqRel is generated in production plant – UN02, but no planned order is being generated. Since there is no planned order in plant UN02, Production is not being carried out.)
If you see 3rd Screen Shot ( Ref. MD04 of UN02) , where in you found planned order is not being generated and as a result procurement and production is not being carried out.
*** Our requirement is explained against point no. 9 to 12 ( once more given below). I got struck at point no 10 and as result we are not able to move forward.
9. After MRP RUN in Plant DP41 (Planning Plant ), a STPR will be created in Plant DP41.
10.Planned order will show in Plant UN02 as the same is production plant.
11.Production & Procurement will be carried out in Plant UN02 on the basis of planned order.
12.Since special procurement 40 is being used, stock quantity which will be produced in Plant UN02, want to transfer from Plant UN02 to DP41 through same STPR through STO.
Please help...
Regards,
Amit Biswas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
As per your screenshot, it looks like your stock transfer requirement is not relevant to MRP. You can observe that the field Available Quantity is empty, which means that the requirement is not relevant for MRP, so no replenishment proposal will be created.
You might have an implementation of BAdI MD_CHANGE_MRP_DATA or MD_ADD_ELEMENTS influencing the standard behavior (see this blog https://blogs.sap.com/2014/10/01/making-an-element-not-relevant-to-mrp-using-badi-mdchangemrpdata/ ).
Alternatively, modification note 190298 - Stock transfer: Order releases are relevant for MRP might be implemented on your system.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.