Guarantee that goods are delivered before payment

0 Kudos

Hi,

Currently we are working on a project to develop a solution that supports the internal purchase process. The idea is: the employee creates a purchase requisition in ME51N; it goes through a customized workflow; if it is validated and approved, the PR will then be automatically converted in a specific type of PO (that we've created to distinguish them from others; let's call it XYZ). Since the PR goes through an extensive workflow of validation and approval, when they're converted in XYS PO, the PO is instantly blocked and released.

To make sure that we don't pay the goods before they arrive, by default, the "Goods Receipt" checkbox on the Delivery tab of items is checked. When the goods arrive, the creator of the PR that originated this PO is supposed to go to the line of the item received and uncheck the "Goods Receipt" checkbox. The problem is that the PO is blocked (so that no one can change the number of units purchased, for example) and so they will not be able to change this checkbox.



Is there a way to block every field except this checkbox? Or is there a way to block the payment until the goods are received? If so, what should we do to indicate that the goods have been received?
(We want the solution to be simple for the PR creator. Currently someone has to uncheck this box on PO so that they can register the invoice. If the solution is "complex" the PR creator could just ignore this procedure, and move on after receiving the goods he/she ordered).

Thanks in advance!

robin_mcrae2
Participant
0 Kudos

Hi Sara,

Is there a business reason for not asking the requester to perform the goods receipt MIGO, rather than giving the requester access to ME22n to disactivate the GR. The GR, MIGO, is normally the control point, which opens the doors for the payment - especially when dealing with quantity disprepancies. Other fun things like visibility in the GR/IR account... then controlling the blocked invoices. Automatic accruals if the GR is done before month end.

Other points to consider - having a dated document. (delivery date )

Just some notions to consider.

Robin McRae.

Accepted Solutions (0)

Answers (1)

Answers (1)

robin_mcrae2
Participant
0 Kudos

Hi Sara,

Sorry - I keep putting my answers in the comments section.

Is there a business reason for not asking the requester to perform the goods receipt MIGO, rather than giving the requester access to ME22n to disactivate the GR. The GR, MIGO, is normally the control point, which opens the doors for the payment - especially when dealing with quantity disprepancies. Other fun things like visibility in the GR/IR account... then controlling the blocked invoices. Automatic accruals if the GR is done before month end.

Other points to consider - having a dated document. (delivery date )

Just some notions to consider.

Robin McRae.

0 Kudos

Hi Robin,

Thank you for taking the time to answer!

The issue is that most likely the people that will create these PRs, after receiving the goods, they will ignore this procedure, and never register anything in MIGO. Also some of these people will only access SAP to create PRs and nothing else, so they might not have much knowledge to do this additional step. That's why we're looking for a simpler solution