How to receive quantity more than ordered quantity against subcon PO

former_member637283
Participant
0 Kudos

Hi All,

Can we receive extra quantity against subcon PO without adjusting components provided? The scenario is as below

Main Material Quantity in Subcon PO : 20

Components required & provided Qty : 20

Main material received quantity is 22. So now if over del tolerance given in PO and GRN posted with 22 then components also gets consumed with quantity 22, which is not desirable in this case. User can update the component qty manually in MIGO, but there is always a chance for mistake..

So to avoid manual intervention, is there any way that the components qty can not be changed, during grn , even if main material qty is more than or less than ordered qty???

Please help.

pataselano
Active Contributor

is the extra quantity to the subcontract PO always without adjusting the supplied components?

If always without adjusting the supplied components then you can try BAdI MB_MIGO_BADI.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member197616
Active Contributor
0 Kudos

Had it been not dependant on subcon bom?

former_member637283
Participant
0 Kudos

Yes it depends upon the BOM..but in some cases cust receives excess quantity..

former_member197616
Active Contributor
0 Kudos

did u get information prior about more qty?

If so possible try receive excess qty by changing po adding additional line as free indicator?