Error in CIG PRD "At least one connection for Testing Environment is required"

Gokulnath
Explorer
0 Kudos

Hi

We are setting up CIG in Production. after the Connection setup when we click next we get error "At least one connection for Testing Environment" in Production environment

cig-prd.png

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member651171
Participant
0 Kudos

Hi Gokulnah,

You cannot create a project directly in Production. First You will need to create a project for Test environment by adding a connection for Test. Then save the project and wait for it to move to status In Testing.

Later once you post the success transaction to Test ,you will start seeing Go-Live button. Upon clicking on that button your project will be moved to production.

More information given below :

https://help.sap.com/viewer/32ba8b3dbca645e9b8b7b3e84d61e3db/2105/en-US/d196ae517e0d42f0aa6406635b9d...

Regards,

Sunitha V S

assad
Explorer
0 Kudos

Hi,

I dont think we can set the connection directly for Production environment. You can add your production connection the project and transport this project to Production by clicking on Go-live option.

Thanks.

Assad