Deployment optimizer is not considering conrel elements of future start date

sumaghosh
Participant
0 Kudos

Hi Experts,

We have Deployment optimizer running every day to generate plans for stock transfers from plants to depots based on depot demand.

We noticed that even if STOs ( COnrel) elements are available system is deploying the unrestricted stocks without the STO quantity subtracted from it.

This is causing huge issue of STO qty > Available unrestricted stock.

Can someone throw some light , how to consider all the STOs as ATI elements irrespective of date.

Thanks.

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Are both input and output dates inside demand horizon?

Best Regards,

R.Brahmankar

Accepted Solutions (0)

Answers (2)

Answers (2)

sumaghosh
Participant
0 Kudos

The issue was resolved by increasing the SNP checking horizon to 5 from 1.

sumaghosh
Participant
0 Kudos

Hi rupesh.brahmankar3,

Yes they are within the demand horizon.

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Did you check the optimizer log?

Where you can analysis which supply elements and dates are considered in deployment run

Best Regards,

R.Brahmankar