What are the major differences between capacity planning in PP and capacity planning in PP/DS?
Hello,
In PP there are limited functionalities for capacity planning as compare with PPDS
In PPDS there are Advanced options in capacity planning
“Pegging” - relationships can be created between product requirements and suitable receipts and Multilevel view of material and capacity availability
You can optimise production plans according to various criteria using optimisation algorithms
Optimization algorithm within the limits of detailed scheduling (minimizing setup times, setup costs, date delays, alternative selection of resource.
To schedule an operation from one alternative resource to another by drag & drop on the Detailed Scheduling Planning Board, in automatic rescheduling or optimization in case of overload, you have to add an alternative sequence to a routing with an alternative work center.
The layout of the planning board can be defined very flexible.
Alert Monitor - Dynamic exception messages (alerts)
Here are some benefits of standalone PPDS solution
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.