Dear Experts,

My requirement: Can I assign a quantity to WBS element or Network and can there be a availability control for that quantity.

Example we created a WBS/Network called Material Procurement - the Quantity we want to plan is sand 100cft, Brick 100pcs(EA), Stone 100cft, Now the control we require is on PO created against , or components assigned to this WBS element should not exceed Quantity + tolerance.

This is just the same scenario as of Budget - we allocate budget and provide tolerance to the budget.

I know Budget Control is available in SAP, but my Requirement is Material Quantity control.

Please help with this