Raghavan,

For linking a document to production order, Please go to SPRO----> document types in the document type you have to establish an object link to the document type and production orders.

Please select a document type and Define object link ---define an object --PORDER with screen 251 and save.

Then go to production---Shop floor control --- master data --Production schedul.profile

and enable - document links material or Bom on release or creation.

Then create a document using CV01N.

Provide the document type and name then enter

In the next screen give the document description and below the originals sub header click on the OPEN Originals.

Here you select your document and attach then save the document.

Now got to CO02 and select the Document overview icon (Next to component overview icon) and provide the details of the operation to which the document to be attached and save.

Document is attached to the Production order.

Else Press go to CO02 and press SHIFT + F7.... then you can attach a document to a production order there manually also.

Regards,

Sundhu

kraghavanbindhu
Contributor
0 Kudos

Can we add the same to operation in routing so that it will be automatically fetched in production order

Answers (2)

Answers (2)

former_member184670
Active Participant
0 Kudos

Raghvan,

Yes correct, while printing the Shop floor paper / Production order report (COOIS) the document will be fetched out.

Thanks,

Sundhu

janbuchmann
Contributor
0 Kudos

You can use list PPIOV000 (Document Links) in COOIS

kraghavanbindhu
Contributor
0 Kudos

How to link the documents to the order. Pls explain