Hello dears,

I have scheduled some accruals in a future date, the problem is, they are not being runned in the system.
Do I have to run them manually?

if yes, that's really hard if we got the frequency period of days, cause I have to run them manually day by day for 365 times.

please let me know if there is a way to let them run automatically if they're scheduled.

I will provide some screenshots so you can check the balance 😄

Please check this link for the screenshots
https://imgur.com/gallery/uOce4Cq

Accepted Solutions (0)

Answers (2)

Answers (2)

nageshpolu
Contributor
0 Kudos

nartlamber_123 : Please reshare the screenshot. We are seeing 404 error.

nartlamber
Explorer
0 Kudos

Thank you for your reply.

please if they didn't open too, let me know 😄

Time Account Type

Time Information

Scheduling

nartlamber
Explorer
0 Kudos

Dear Nagesh,

please check the comment in Sem's comment 😄

semmeereboer
Explorer
0 Kudos

Hi Nart,

What you're asking is a lot to answer in one post.

It is possible to schedule automatic accruals, refer to the implementation guide by SAP: https://help.sap.com/viewer/68de09dff990417b9f0acf6ccc13a14d/2105/en-US

Kind regards,

Sem

nartlamber
Explorer
0 Kudos

Alright mate, will dig into that 😄

nartlamber
Explorer
0 Kudos

Dear Sem,

after checking the system, I got into a KBA which says it has to do something with the trigger jobs in provisioning.

Please check this KBA for more info, " https://userapps.support.sap.com/sap/support/knowledge/en/2594441";

KBA number : " 2594441"

is that what you are referring to? or it needs even more to answer in one post ?