network settlment and project settlement

101 Views

Hi

we have a customer projects of 4 level wbs's. 4th level there is account assigned and billing element ticked, underneath 4th level wbs we have network being created with all 4 types of activiies, meaning cost will hit at network level as well.

we are not doing RA, and all the cost and revenue will sit at 4th level wbs.

my question is network settlment to 4th level wbs is required here? or since network is assinged to 4th level wbs, so all the cost is automatically rolling up to 4th level or network settlment to 4th level is required...

Secondly, any suggetion without RA - from 4th level wbs can we settle to Costcenter ? and for project progress report and results report - which reports to consider apart from SLR regular reports?

thanks

Pkg