May 25 at 11:08 AM

Weekly Regenerative MRP job is converting Lead time PRs to Planned orders

86 Views Last edit May 25 at 11:14 AM 2 rev

Hi Experts,

We have Daily NETCH MRP jobs running on Weekdays and Regenerative MRP jobs running on Weekends.

We are observing a strange behavior of Externally procured materials. If the MRP run date falls under lead time(mentioned in MRP 2 view) of material, then NETCH job is converting its planned order to PR automatically which is as expected but the Regen job which runs on the following weekend is converting it back to Planned order (If the PR is not converted to PO yet).

The Jobs are being executed in background using MDBT tcode program RMMRP000.

Can anyone explain why its happening and is there any way to handle this situation if its expected behavior.

Thanks

Shikha