Hello All,
I searched a lot in the portal but was not able to find a similar question. That is why I am posting this question.
We have an equipment which is used as a PRT in a Routing, which is further used in Production Order.
We have already created a measuring point for this equipment. While confirming the production order a new measuring document is being created for this equipment.
But when I am using the same settings and the same process for an equipment from an equipment hierarchy it does not creates a measuring document while confirming the production order.
I have tried this with the parent equipment and the child equipment, but it does not work in both the cases for me.
Please can anybody suggest that what I doing wrong here or am I missing something.