on 05-12-2021 8:30 AM
Hello All,
I searched a lot in the portal but was not able to find a similar question. That is why I am posting this question.
We have an equipment which is used as a PRT in a Routing, which is further used in Production Order.
We have already created a measuring point for this equipment. While confirming the production order a new measuring document is being created for this equipment.
But when I am using the same settings and the same process for an equipment from an equipment hierarchy it does not creates a measuring document while confirming the production order.
I have tried this with the parent equipment and the child equipment, but it does not work in both the cases for me.
Please can anybody suggest that what I doing wrong here or am I missing something.
Abhishek Ashish,
Just a thought..
In IE03, go to the status overview screen and click on the Business Processes tab, then check the items to see if "Use production resource tools" is permitted.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Peter,
Thanks for the support.
I tried to dismantle both the Equipment. Once the child and the other time the Parent, and again Installed both of them but still the problem persists. When I create the production order and confirm it, the document is not getting created automatically.
Is there a process difference between an equipment with a structure and the equipment without a structure?
Regards,
Abhi
Abhi,
Have you tried dismantling the equipment - then test them in a production order (before installing them again later ).
This will test if the same equipment PRT will work in a production order when it is not installed..