on 02-20-2017 1:42 AM
Dear Experts,
We're using SAP ECC6.0 (No EPH). Recently I found a tricky issue about PIR reduction, would you give hands and help?
Background: Strategy Group 40, default Setting with class type 101 & 50.
It seems ridiculous, do you think so? Why SAP change the original PIR planned qty when reverse a DN? Imagine that users just create/post a wrong SO/DN and then reverse them, do I have to get additional PIR? How to reslove this?
Thanks & Best Regards,
Hello
I don't think you can change this system behavior.
Take a look on the following note, which explains this logic and the restrictions behind it:
Regards,
Caetano Almeida