on 05-07-2021 8:47 PM
Hi guys,
I want to follow requirements of semi-finished products as a make to order.The main product is also make to order.So how can ı state that in Sap S4
<br>
Hello
In the material master MRP4 tab you will find the field "Individual/Collective". If you want a semi-finished product to be kept under the sales order stock, set this field to 1 - Individual.
If there are orders already created you may have to re-explode the BOM.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Since Each product of the demand will be separate one, you can maintain the strategy grp as "20 -Make to order) in material master MRP 3 View.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.