Scheduling Agreement Update Automatically

0 Kudos

We are creating scheduling agreement w.r.t "SAP Contracts". Scheduling agreement is created for long validity period i.e. from Jan to Dec. Whereas prices in contract keep changing time to time with different validity periods. So my query is will Scheduling agreement update price automatically according to price validity period mentioned in contract?

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please refer SAP KBA 2633745 - Price changes is updated from Contract to Scheduling Agreement

When an SA is created with reference to a contract without maintaining separate conditions in SA, the price displayed in SA is the dynamic price of the contract. Once the SA is created, it will not check the contact status again during price determination.

Best Regards,

R.Brahmankar