Hi guys,

Just need help in creating a transport strategy.

We have a BAU landscape and planning to have a project landscape. My concern is how can we move transports from Prod to the Project Dev system?

2 options that I am thinking:

1. No change in transport routes but instead, we will encapsulate the transports from BAU in a TOC then move the data/cofile from BAU to Project trans directory. Incase of this option, we will create 2 TOC, 1 for all workbench requests and 1 for all Customizing requests.

2. Create the transport delivery route from Prod to Project Dev

What do you think is the best option? Or if there is other options, please let me know.