Me gustaria saber si a nivel de plan de mantenimiento existe la posibilidad de hacer una diferenciacion en la generacion de las ordenes en fechas. me explico, en nuestro caso tenemos un mantenimiento que debe realizarce cada 12wk, pero no deben salir todos en una misma fecha, se puede de alguna manera ajustar la fecha de inicio de ordenes para cada equipo sin tener que cambiar el paquete de MP en el Task List?
Hi Peter
Thanks for your support, We will create a plan per equipment
Kind Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Henry,
If you had a single plan, with multiple maintenance items (each with one equipment), then all the orders would be created on the same date. This means that you wouldn't be able satisfy the requirement in your initial post. Also any rescheduling of that plan impact all maintenance items/equipment.
So if you need complete flexibility, then have one plan per equipment.
Alternatively, have 52 plans (one for each week) and put the equipment in the correct plan.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Peter for your answer.
so in a single plan where I have all the equipments and all the task list is it not possible to do this?
This due to the fact that I have many equipments so it would require many plans to control
Kind regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Henry,
In SAP we would create 2 maintenance plans, one for each equipment.
Then they would be scheduled (via IP10) with a 1 week offset.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Peter thanks for your answer.
let me try to explain a little bit my question:
We in our current manitenance system have activities that are common in different equipments. these activities for example, have a frequency of 1 weeks, the detail is that in the same week we cannot carry out 2 equal activities for different equipments, this due to resource and time. for this reason, what we currently do is make them move vy dates, example:
*Equipment 1 start in week 2 next activity will be in Wk 14
*Equipment 2 start in week 3 next activity will be in Wk 15
and in this way wih the other equipment, thus we managed to have a differentiation of dates avoiding coincidence in dates and respecting the frequency.
In SAP we can have a single plan and assign the dates in such a way that the activities and the frequency are same but that the ordres for the equipments are generated in different weeks?
Kind Regards