sales schedule agreement with FRC and JIT

I want to use the FRC and JIT in the sales schedule agreement at the same time.but the RFC datas are just for the record, it can't be used for MRP and DN; I wish the JIT datas running MRP and creating the DN. How to do?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 05, 2017 at 06:41 AM

    the Standard Type LZJ and LZ is for Customer Schedule Agreement(CSA).

    LZJ is for JIT Call, that applies EDI. the FDS and JDS can updated by EDI data.

    LZ can add FDS and JDS manually.

    FDS is not used for DN, only JDS is for DN.

    Both of them, there have JIT horizon, JDS fall in before horizon and FDS fall in after horizon both will be shown in requirement list MD04.