on 02-25-2021 5:43 AM
We are doing partial conversion of planned order to production order in C048 T.CODE ..If the planned order Qty is 50 kg.System should not allow to convert more than 50 kg in partial conversion of planned order to production order in C048 T.CODE .System should through error msg..more than the planned order qty is not allowed.
Hello,
Please try the BAdI WORKORDER_UPDATE method AT_SAVE to validate planned order quantity AFPO-PGMNG with order quantity while save the production order.
Best Regards,
R.Brahmankar