hi,

i am able to email the purchase order when it is getting saved, ( following the procedure in sap note 191470 ), but the requirement is it has to be mailed at the time of final release. plz suggest me a solution.

thanks and regards,

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Apr 27, 2006 at 09:55 AM

    Hi Santosh,

    This is already working like this in SRM.

    The output is executed at the time the PO is ordered (after final approval step).

    I would be really surprised if MM was sending the PO before its release !!!!!

    It should be standard.

    Have you tested it ?

    Have you posted the same question in ERP forum ?

    Rgds

    Christophe

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 27, 2006 at 10:03 AM

    yes christophe, i have tested it i am getting po as a pdf attachment as soon as the it is getting created(i.e. when i press the save button).

    but how should i restrict it till the purchase order gets released.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 27, 2006 at 11:42 AM

    plz suggest some solution as soon as possible,

    its really urgent.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Santosh

      In SRM there is no release procedure as you find in R/3 MM. Instead SRM is having workflow for PO through which you can build the same logic as release procedure does in R/3 MM. For this you need to activate the PO workflow in SRM which will trigger when you create PO.

      So when you click create PO button in SRM(assuming you are in classic scenario), PO workflow would get triggered. After it is approved(through workflow) PO gets created or released in R/3 MM.

      Hope the above solution would be helpful.

      Regards

      Jagdish

  • avatar image
    Former Member
    Apr 27, 2006 at 03:58 PM

    hi jagdish,

    we have MM r/3 here, now kindly suggest me the solution, its really urgent, i have trieed a lot of things but nothing has worked out.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Santosh,

      As I already asked: have you posted this question in ERP forum ?

      I think that PO output is done at save time because you asked for it in ME22N.

      You could block this assigning a specific edition routine to your message type. In this form, you could control the release status.

      Have you tried not to enter manually the output type ?

      I mean did you try the standard message determination technic. So, based on defined conditions (access sequence), the system will create a message for your PO or not.

      I think/hope that in that case, the release status should be taken into account.

      Rgds

      Christophe