on 02-08-2021 10:29 AM
Hello,
My client is procuring Microwave and this microwave will be use by 2 different Departments i.e. A & B so now Finance requested to split the expenses into two different cost centers 50% go to A and 50% go to Dept B.
Can you please share some document how can I do this?
Thanks,
For your PO with account assigned- In account assignment TAB of PO item Detail, keep
Quantitate----------------- Cost center- G/L account
0.5-------------------------------C1---------------G/L-1
0.5-------------------------------C2--------------G/L-2
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi - this is documented in the SAP Help - https://help.sap.com/erp_hcm_ias2_2015_02/helpdata/en/b4/7db65334e6b54ce10000000a174cb4/frameset.htm - multiple account assignment
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.