Hello,
I have tried searching but cannot find a solution. I am currently using SAP Business one version 10.00.140 HANA.
The company I work for is completed production orders once they are fully complete and not at each work center. They are interested in moving towards completing at each work center. I believe I have an understanding of how to set it up, however, I'm curious about the reporting side.
Is there a way to see the status of a production order that is partially complete? If so, how to I find it? Being able to see the report would help show others it is a useful and thus making the switch.
And recomenedations would be appreciated.
Thank you,