Maintenance Order - specification of a time period

114 Views Last edit Dec 21, 2022 at 02:17 PM 2 rev

Hello Experts,

We have the problem regarding maintenance orders that we can only specify a duration for the maintenance. However, we need a concrete time table, which cannot be specified at the moment.

We also could not find any functionality where we could enter the maintenance order into a concrete time table afterwards. If we can only define a duration, the maintenance window will be scheduled according to the shift calendar at a free period and not at our required time.

Requirement: During the maintenance window (e.g. from 1 pm till 6 pm) the workstation should not be available for production.

Is there no way to do this for maintenance orders?