Hi, Experts,

We have this case,

during produce process for FG A, because some reason , some produced qty need to be goods received as FG B urgently. and can not wait office member create prod order for FG B

Currently user will create prod order with large qty for FG B in advance, when have this case , they do GR based on this prod order.

but it will cause planning incorrect.

So is there any way can let production can do GR for FG B urgently,also consume raw material and have cost ,but not effect planning?

for example: sys create prod order and backflush for FG B based on GR automatically?

RGDS