cancel
Showing results for 
Search instead for 
Did you mean: 

Mass processing transaction in pp orders

Suresh369
Explorer
0 Kudos

Hi,

We have 450000 production order pending to set DLFL and DLT status. I tried the program PPARCHP1 by mass setting in back ground. But in this program only 240 orders status completed per hour. so it takes around three months to complete. How to speed up my process. Kindly suggest is there is any way to solve my problem.

Regards

Pugazhendi Subramani.

Accepted Solutions (0)

Answers (0)