cancel
Showing results for 
Search instead for 
Did you mean: 

Is it possible to reset the processing status of an investment project

Greetje
Explorer
0 Kudos

In the ECC SAP systems it was possible to reset a processing status of a project/WBS element from released to created or from closed to released. Is that also possible in S/4HANA Cloud?

Accepted Solutions (1)

Accepted Solutions (1)

Corey
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi g.gompelman-kooima ,

It is impossible to change the status from released back to created.

However, it should be possible to change the status from closed back to completed then back to released.

You may refer to this on-line help .

https://help.sap.com/viewer/f369b2eff700401494ba6e7c9a573288/2008.500/en-US/d442899643f342e3af889580...

Thanks and regards,

Corey

Answers (1)

Answers (1)

OwenLiu
Product and Topic Expert
Product and Topic Expert
0 Kudos

Move to the correct LoB.