In the ECC SAP systems it was possible to reset a processing status of a project/WBS element from released to created or from closed to released. Is that also possible in S/4HANA Cloud?
Hi g.gompelman-kooima ,
It is impossible to change the status from released back to created.
However, it should be possible to change the status from closed back to completed then back to released.
You may refer to this on-line help .
Thanks and regards,
Corey