on 08-21-2020 5:21 AM
Dear Expert: Take an example to explain our requirement: We have a BOM structure: Material: A (Finished products). Material B and C(semi-finished products). Material: B1 and C1(Raw material). Currently, we need create Production order for A and B, C manually. We want to know if there is any setting or APP can let the Production order for material B, C generated automatically when create Production order for material A? Best Regards Kane
Hello Kane.
How are you? In S/4HANA Cloud, there is no automatic and direct Production Order for the Component of a Production Order. To create all the Planned Orders for the Semi Finished Components, I recommend to execute the MRP for the Finished Product and all the Semi Finished Components will have the Planned Orders created. Then, you can convert them in Production Order.
Regards.
Juliano Romanato.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.