Project Budget Control

287 Views

Hi,

I would like your help on the following.

I have used "Import finance plan data" app to upload budget by WBS using "Project budget template" in BUDGET01 planning category.

I correctly display values in "check financial plan data" and in report "P&L Plan/Actual" but there is no way I can see them in "Project budget control" report. That never reports results in any WBS/GL account. Do you have any idea why this happen? Is there any alternative report I can use to control budget by WBS? and compare actual vs budget? Anything I should configure/check?