Skip to Content
0
Jun 22, 2020 at 08:40 AM

WBS planning and Confirmation

325 Views

Dear Team

I have Created the Project and also create WBS elements , for each WBS element i have done planning , by mentioning basic date and duration , which we can see in project planning. in the form of gantt chart.

I have also updated actual start date and actual completion date against each WBS and after that complete the WBS . I can see WBS is Completed in as the color of the bar get changes.

but i am not able to compare plan vs actual for the WBS element in the planning board , if there any seprate report to track this please let me know .