Dear Team,

I have created PR from doc type Outline agreement requisition further for creating contract from create contract order tile  i am getting error for DOC type is not assigned to contract doc type I am sending you screen shot please find it. 

So for assigning PR document type to contract where i need to go in Manage your solution please suggest on same 

Accepted Solutions (1)

Accepted Solutions (1)

Anupam1
Advisor
Advisor
0 Kudos

Hi Prajyot,

In Manage your solution app, under souring and procurement application area,select requirement processing and goto define document types.click on configure. In the next screen select the document type RV & click on link purchase requisition-document type, check whether the contract document type is mapped or not.

Hope this will resolve your issue