on 06-07-2019 10:39 AM
HI everyone,
we have the following problem. We have one material in stock which currently has the unit "liter". We would like to change this unit to "piece".
Is this possible and if yes, how can we do that?
Thanks,
Markus
Hi Markus,
You can use the app 'Change Material' to change your base UOM only under the following conditions:
1. If there are no stocks of the material in the current period and in the previous period
If there are stocks in the previous period, you can clear them as follows:
a) Post the stock in the previous period to the current period (for example, using movement type 561) so that the stock for the previous period is the same as the stock for the current period.
b) Clear the stock with the posting date in the previous period (for example, using movement type 562).
2. If no purchase requisitions, purchase orders, or scheduling agreements exist for the material
Please note that you may also consider instead maintaining the conversion to an alternative UOM (piece) and setting this as the sales unit for example.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I wanted to follow up to see if the resources suggested were helpful. Do you have an answer for your question?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Here are some SAP resources you may review based on your topic "material,change,stock"
Manage Material Coverage
With this app, you can solve any coverage issues for your materials based on ... to check how the stock/requirements situation changes for the selected material.
https://fioriappslibrary.hana.ondemand.com/sap/fix/externalViewer/#/detail/Apps('F0251')/S8OP
Overdue Materials - Stock in Transit
You can identify these materials to complete the stock transfer process or investigate potential ... Display Price Change Documents, Display Price Changes .
https://fioriappslibrary.hana.ondemand.com/sap/fix/externalViewer/#/detail/Apps('F2139')/S9OP
2584465 - Negative Stock Not Permitted in Logistics Area and ...
2584465 - Negative Stock Not Permitted in Logistics Area and Material While Post ... Go to Change of Stock subview; Enter the required Site and Planning Area.
https://apps.support.sap.com/sap/support/knowledge/public/en/2584465
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.