Skip to Content
0
Jan 31, 2021 at 09:42 AM

How to report material consumption as WIP working with cost collectors?

29 Views

With costcollector WIP is calculated at the moment of confirmation.
Currently if the raw materials are already consumed on a production order, but if at month end there is not yet a confirmation on the order, the raw materials fall into consumption in the P&L. Whereas they should be in WIP.