Hi all,

I have checked the box for completion requirement on the maintenance plan.

The time frame set is to generate an order each week.

The first order generated by the maintenance plan was closed (TECO) a week later than the actual plan date.

First order generated on - 11/01/2021 ; Planned date of next order - 18/01/2021

First order TECO - 19/01/2021

Which means the next order must be generated on 26/01/2021 since I checked the completion requirement box, But the problem is it's been more than a week and still I am not able to see any generated orders.

Please let me know the possible solution.