Hi,

In a change record when defining the route for the tasks to be executed we see that tasks a sequential BUT is there a possibility to define tasks that can be done in parallel? There is a field "step to be completed"

* one of the recipients

* all the recipients

Is this what we need to define a parallel track of how can this be modelled?

kind regards,

Eric

Accepted Solutions (1)

Accepted Solutions (1)

Enda
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Eric

The App Change Record only allows sequential tasks at the moment . parallel isnt available . Development are aware of the requirement and are trying to included it in the future. Unfortunately a planned date / release is unknown .

I Hope that answers your question.

Enda

Answers (1)

Answers (1)

Enda
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Eric ,

Im checking with the owners of the App if parallel is possible .

Il keep you informed.