Jan 26, 2021 at 08:41 PM

CMP2 plan hours disappears in workforce planning

83 Views

Hello,

When changing the dates in the activity in CJ20N (constrains start or finish date), plan hours disappears from CMP2 workforce planning. I've found SAP note 2477279. My configuration in OPU6 for rescheduling is "delete work outside the new dates". I think the latest scheduled dates are taken into account.

Is there anything I can do to keep these dates from changing or to prevent rescheduling being called when saving changes in cj20n? Or maybe some other configuration should be changed?

Thanks in advance for all suggestions!

Best regards

I.