0 Kudos

In Redwood BPA, what happens to the status handler when you nest a job chain within a job chain, is the status handler of the sub job chain taken into account or is only the status handler of the master job chain taken into account? I noticed for a step in the master job chain status handler I can set Restart failed process current, but will that restart the specific step in the sub job chain that failed if it containes multiple steps?

Accepted Solutions (0)

Answers (1)

Answers (1)

gmblom
Active Contributor
0 Kudos

Hello,

No it would only restart the failed processes in the step of the master chain. So that could be the entire sub chain if that sub chain fails.