Dear all experts,
I have below business case:
Plant A - Finished Goods Plant (Material A is only extended under plant A in material master)
Plant B - Raw material Plant (Material B is only extended under plant B in material master)
I am going to create a BOM by using T-Code CS01 under plant A. I enter material A as BOM parent material under plant A and material B as BOM component. After I entered the material B, the system prompted error message to say "Material B not maintained in plant A".
Is it a must that both material A and B have to be extended to the same plant before creating the BOM in CS01? Thanks.