Hello Experts,

The system captures Actual Production time when we perform Start Activity & Finish Activity.

But sometimes we won't be able to capture this due to various reasons. In such scenarios, we directly change the status of Production Task to Status Finish to complete the task.

Here system doesn't allow to record actual production time (& gets cleared as per planned time) hence there is a mismatch in actual vs planned production data.