Hello people.
I have the following scenario:
- A project with a network diagram and internal activity.
- For this internal activity, a material is included that generates a purchase requisition plus a reservation.
- There is a material contract with an item that has the material included in the activity.
- The contract and contract item are entered in the fields on the purchasing data tab.
- The Price field has no value.
It was expected that the price of the contract item would be considered and brought to the corresponding field.
- There is a situation similar to this for services and the system brings the price of the service contract item to the network activity.
Why is the contract item price not considered in the case of the material?
Thank you very much.