Changing root attribute of WKPRODLOC Planning level

80 Views

Hi experts,

Hope all are doing well.

I have a question regarding changing the planning level root attribute of WKPRODLOC Planning level. We have maintained lead times in Weeks in Location source master data. However, system is giving us wrong output for lead time.

Example: we have maintained lead times of 17 weeks. Heuristics output is planning at 15 weeks as it is considering 2 technical weeks in the calculations.

It is completely wrong as far as the output is concerned.

Can we change our root attribute of WKPRODLOC Planning level from tech week to weeks now? What effects it would have on other planning levels or what other changes we need to incorporate for proper results.

Thanks in advance

Regards

Ajit Jadhav