Hi experts,
We have done config including plan version/ scenarios and mapped correct Resource types.
Resources are created and are assigned to Cost elements/ Act types.
Org structure and all is maintained as well. Cost center default and KP26 rates are maintained.
When we launch KP26 based planning monthly/ daily or even output based planning, for a quotation based on Master project structure or Bid structure, it does not show my resources. When we check list in analysis tab> display, all resources are visible but not able to plan. BW reports are run as well to replicate to infocubes. Valuation strategy and methods are also defined.
I get warnings that qty, rate cost etc all not input ready. We are on ECC with CPD2.0007
Any pointers?
Rgds,
Niranjan