on 11-05-2020 7:39 PM
Hi PS Experts,
We have a scenario where the BOM is exploded in PS eventually creating reservation for network .
Item category is L(Project stock).
The Material is HAWA similar to FERT. MRP is run for the fulfillment.
The ask is to bring the same to ‘Unrestricted Stock’ or ‘Plant Stock’ rather than Project stock.
Is there a way to achieve the same. Please share your suggestions.
Let me know if you need further info. Please cascade the same to members if you know from PS.
Best Regards
Guru
Look at the Individual/Collective indicator in the Material Master. That is what determines if a material plant or project stock.