APO PP/DS - schedule lines created on Sunday - a non-working day

228 Views

Hi,

the product heuristic - 3 horizon heuristic with daily lot-size creates schedule lines on Sunday - a non working day according to factory calendar (no planning calendar is maintained in the product master). The factory calendar is assigned as the receiving calendar in the location master. the periods in the calendar are Mon-Sat, all correct.

I cannot explain myself why? Also why the time fence is displayed on Sunday when it is not a working day.?

kr,

Walter