cancel
Showing results for 
Search instead for 
Did you mean: 

Lead Time in Delivery of a Procured Item

0 Kudos

Hi,

In our company, we have a machine part no (say A) which is of E type. Under this part, there is an import part which is of F type (say B). Now this import part needs to arrive at our plant before 1 month of the actual production schedule. Now if I create a planned order of part A (inhouse production time = 2 days), the dependent requirement of part B is getting generated on the start date of the planned order of part A which is okay.

Now the schedule line for part B is also getting generated on the same day as the dependent requirement date as per MRP.

If I have to generate the schedule line say 30 working days prior to the dependent requirement dates, what should I do?

mynynachau
Community Advocate
Community Advocate
0 Kudos

Thank you for visiting SAP Community to get answers to your questions. Since you're new in asking questions here, I recommend that you familiarize yourself with https://community.sap.com/resources/questions-and-answers (if you haven't already), as it provides tips for preparing questions that draw responses from our members. For example, you can outline what steps you took to find answers (and why they weren't helpful), share screenshots of what you've seen/done, make sure you've applied the appropriate tags, and use a more descriptive subject line. The more details you provide, the more likely it is that members will be able to assist you. You should also make sure you're using all the appropriate tags, so the right experts can find your question.

Should you wish, you can revise your question now by selecting Actions, then Edit.

Finally, if you're hoping to connect with readers, please consider adding a picture to your profile. Here's how you do it: https://www.youtube.com/watch?v=F5JdUbyjfMA&list=PLpQebylHrdh5s3gwy-h6RtymfDpoz3vDS . By personalizing your profile with a photo of you, you encourage readers to respond.

Best regards

Mynyna

SAP Community moderator

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hi Soumyadip,

I forgot the mention that the offset date will not reflect on the schedule line directly. For example you have production order, when you look at the component list as the effect of lead time offset, the requirement date (can be seen under requirement date tab) of that material will be -30 days (Production Start Date - Lead Time Offset).

Lead time offset don't directly affect the proposals made during MRP Run. Lead time offset will only affect the requirement date of the component materials during BOM explosion. Please verify the start date of your planned orders.

If the component has lead time offset. Start date of planned order - Lead time offset = DepReq requirement date.
In terms of production/process orders. Start date of order - Lead time offset = OrdRes requirement date.

I hope I was able to explain the point well.

BR,
Darryl

0 Kudos

Hi Darryl,

Thanks a lot for your explanation. My query is resolved.

Regards,

Soumyadip.

Answers (2)

Answers (2)

Abdul
Active Contributor
0 Kudos

Try to increase the lead time after adding the 30 days prior to production like if lead time is 10 days and you need that part 30 days before production use lead time of 40 days in master data of item.

0 Kudos

Hi Soumyadip,

You can use the planned delivery time and GR processing time in MRP2 view. Sum of planned delivery time and GR processing time will be the availability date of material B. You can maintain 30 planned delivery time and 0 GR processing time or the other way around depending on your business process. If you are using a non-stock material in your BOM, you can use the lead time offset field, say -30 days. Meaning material will be scheduled to be received 30 days prior to the start of the production.

Hope this will help

BR
Darryl

0 Kudos

Hi Darryl,

I maintained 30 days as the planned delivery time of the F type material in material master. After running the MRP, the schedule lines are being generated on the same date as the dependent requirement not 30 days prior. I am attaching screenshots of material master & md04 screen of the F type part.

material-master.jpgmd04.jpg

Regards,

Soumyadip.