QM Inbound Certificate at time of Inspection Lot Processing & Usage Decision

237 Views

Hello experts,

We want to acknowledge incoming quality certificate receipt at the time of inspection lot processing and UD recording. Is it feasible to have this functionality of checking for an inbound certificate at the time of UD and If yes, then how can it be achieved? Specifically, the following configs have already been done-

A QM control key with indicator Certificate required is set

  • A certificate type has been defined and the indicator for enhanced certificate processing is set
  • A number range for the certificate receipt is defined
  • In the material master, the following conditions are met:

  • QM in procurement is active
  • A control key with certificate requirement is set
  • A certificate type is specified
  • However, neither inspection lot status is updated or UD is blocked so far when we create the PO, inbound delivery for that PO, GR against the inbound delivery

    Also, is Quality Info Record a mandatory master data to cater to inbound certificate receipt functionality?

    Please advise on how we can proceed further.