Period work schedule

0 Kudos

Hi Gurus,

I have to generate the calendar for next 4 years as required by client.

that too with second sat as H/D and 4th sat as official off.

Generating PWS 52weeks *4 is not possible

Also i need to configure holidays accordingly

Please suggest! its urgent

dschmidt
Explorer
0 Kudos

Hi, you got the standard report RPTSHF00 to generate entries in table T552A.

If that wasn't your question, please provide some more detailed information what your actual problem is.

Best, daniel

Accepted Solutions (0)

Answers (1)

Answers (1)

BalaAP
Active Contributor
0 Kudos

dnschmidt is right. But usually we generate this once in a year (during year-end, once they freeze the holiday list for next year. If you find it difficult for 4 years at once, you can do it year by year.